●The actual configuration of a PERT/CPM network _____ the amount of resources that can be

● The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project. A Increases. B Is not affected by C Does not require D Is heavily dependent upon E Is the only means of determining