You are working on the cost budget for one project. Which of the following is true()

A . This process assigns cost estimates to project activities including risks and contingency plans. B . The cost baseline will be used to measure variances and future project performance. C . This process assigns cost estimates for expected future period operating costs. D . The cost baseline is the expected cost for the project.