A report of casualty to a mobile offshore drilling unit must include ().
After conducting an abandonment drill,the Master or person in charge of a ship shall log().
Under the regulations implementing MARPOL, a mobile offshore drilling unit is required to have an International Oil Pollution Prevention (IOPP) certificate when the unit ().
According to the regulations for mobile offshore drilling units,“industrial personnel” are considered to be all persons carried on the ship for the sole purpose of carrying out the industrial business of the unit,except for().
Each drilling unit equipped with helicopter fuel storage tanks must have the tanks installed as far as practicable from the().
In securing deck loads for an ocean tow,drill pipe should be().
An offshore drilling unit is required to carry on board an operations manual approved by the ().
A documented vessel operating over 50 miles offshore must carry an inflatable liferaft with a ().
To determine what navigation lights and day-shapes must be displayed on mobile offshore drilling units under tow,you should check the().
Fire protection regulations for towing vessels require that drills be conducted on board the vessel as if there were an actual emergency. Drills include all of the following,EXCEPT().
Temporary Certificates of Inspection for offshore drilling units are effective until the ().
After reporting a casualty to a mobile offshore drilling unit,which record must be retained on board? ()
In the case of an injury causing a person to be incapacitated,the Master or person in charge of a mobile offshore drilling unit must submit a report to the().
Prior to backloading portable tanks or drums onto an offshore supply vessel,check that each tank is().
When making landfall at night,you can determine if a light is a major light or an offshore buoy by().
Each emergency generator on a mobile offshore drilling unit,when tested,must be run under a full load for at least().
During an abandonment or drill,the first person to arrive at the survival craft should().
If passengers are on board when an abandon ship drill is carried out,they should().
When a marine surveyor is employed to assist in the move of a mobile offshore drilling unit,he().
What is the most vulnerable part of the fire main system on board an offshore rig?()
To determine the number of Able Seamen required on a mobile offshore drilling unit,you should check the().
A jack-up drilling unit elevated on the Outer Continental Shelf must have a fog horn that will sound().
Fire protection regulations for towing vessels require that drills be conducted on board the vessel as if there were an actual emergency.Drills include all of the following,EXCEPT ______.
According to the regulations for mobile offshore drilling units,"industrial personnel" are considered to be all persons carried on the ship for the sole purpose of carrying out the industrial business of the unit,except for ______.