Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()
A . Order a POWER5 HMC
B . Connect to the existing HMC
C . Install an 8-port asynchronous card in the managed server to connect to the existing HMC
D . Install an additional network card to the existing HMC and connect to the POWER5 service processor
-
Company.com has crated a process application monitor for an application that is initiated by a "c" Shell script. The application monitor is not functioning as designed. What could be the issue with eh application monitor?()
A . A process monitor cannot monitor an application started by a shell.
B . For process monitors to function correctly, they must use the "korn" shell.
C . A custom monitor cannot de3termine the status of applications started by shell scripts.
D . The process monitor script is not existing with a zero return code after checking the status of the application.
-
Company.com has encountered a problem on the HMC, which requires access to the root shell on the HMC. Which of the following is necessary to access the root userid on the HMC?()
A . Enable remote commands on the HMC Configuration menu,then use ssh to login to theHMC,enter su - root
B . Login to the HMC as hscpe and run pesh,using a temporary password from IBM Support,afterward, enter su - root
C . Login to the HMC as hscroot,then run pesh,using a temporary password from IBM Support, afterward,enter su - root
D . Enable remote commands on the HMC Configuration menu,then telnet in as hscroot,entersu - root
-
Company.com has purchased a 2-way p5-520 and would like to create three Micro-Partitions on the server. Which feature of Advanced POWER Virtualization would allow them to create the desired number of partitions?()
A . Virtual Ethernet
B . Shared Ethernet Adapter
C . Dedicated Processors
D . Shared Processor Pool
-
Company.com with an EtherChannel implementation is considering an HACMP solution. What considerations must be addressed in planning this configuration?()
A . Hardware address takeover must be configured.
B . IPAT via IP aliasing is required for EtherChannel.
C . EtherChannel must be defined as a separate network.
D . HACMP does not support the fallover of EtherChannel.
-
Company.com is adding a new I/O drawer to an existing p5-570 with four LPARs and wants to re-balance the network cards in the I/O drawers. What is the best way to accomplish this?()
A . Add the devices as virtual adapters to a VIO server first,then add the I/O drawer and create the shared ethernet adapters
B . Power down the partitions,run the diag a command when the system is brought back up and reconfigure the network cards
C . Use the rmdev command to remove the devices,shut down the partitions and move the cads,then run the cfgmgr command after reboot
D . Detach the network cards,run rmdev on the devices and then dynamically reassign theadapters to the partitions and reconfigure
-
Company.com has decided to implement the "Fast Disk Takeover" and "Disk Heart Beat" features of HACMP. What IBM distribution media will be required for a default installation?()
A . AIX media only
B . HACMP media only
C . AIX and HACMP media
D . HACMP and Concurrent Resource Manager media
-
Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()
A . Configure a Shared Ethernet Adapter on the Virtual I/O Server.
B . Use the same virtual LAN ID on each LPAR.
C . Set up IP routing through an LPAR on each system.
D . Set up an IP firewall through an LPAR on each system.
-
Company.com has a 2 processor license for SLES 9 and a 2 processor license for AIX V5.3. Which of the following LPAR configurations is valid on a 4-way p5-550?()
A . SLES9:2 dedicated processors AIX: 2.0 processing units,4 virtual processors,uncapped
B . SLES9:2.0 processing units,2 virtual processors,uncapped AIX:2.0 processing units,4 virtual processors,capped
C . SLES9:2.0 processing units,3 virtual processors,uncapped AIX:2 dedicated processors SLES9:2.5 processing units,3 virtual processors,capped
D . AIX:1.5 processing units,2 virtual processors,capped
-
A customer has an EMC Symmetrix DMX-4 installed. The disk subsystem is coming off lease. The customer is considering an IBM System Storage DS8800. What is a key advantage of the DS8800()
A . The DS8800 has a higher disk RPM than the Symmetrix DMX-4
B . The DS8800 has higher capacity with more efficient footprint than the Symmetrix DMX-4
C . The DS8800 supports FlashCopy for internal array replication
D . The DS8800 supports external virtualizatio
-
Company.com complains that an outage is required when adding a new filesystem to cluster. The System management function of HACMP (C-SPOC) functions in which manner when adding filesystems to a cluster?()
A . Adds to all nodes with the cluster running.
B . Adds to all nodes with the cluster stopped.
C . Adds with the cluster running,uses "Lazy Update" to perform the logical volume synchronization.
D . Adds to all nodes with the cluster running but requires the volume groups to be exported andimported after.
-
Company.com has an application that requires a serial connection for Electronic Data Interchange. What must be done to integrator the serial connection into an HACMP cluster?()
A . Use an RS3232/422 serial Y cable.
B . Alter the device settings to 9600 8/n/1 xon/xoff.
C . Use a network based terminal server for the serial connection.
D . Nothing because HACMP does not support native serial connection fallovers.
-
A customer with an EMC Clariion CX700 storage installation is considering a new IBM TotalStorage DS4500 solution. Which of the following is an advantage of the IBM DS4500 solution?()
A . Host port speed of 2Gb/s
B . Three-year hardware warranty
C . Heterogeneous Operating System support
D . Storage Manager software comes standard with DS4000 controller
-
The customer has recently installed a pSeries p5-570 with EMC attached disk storage. After installation, the customer complained that the disk access appeared to be too slow. How should the pSeries technical specialist best assist the customer?()
A . Recommend the customer call EMC.
B . Recommend the customer call IBM hardware support.
C . Recommend the customer contact SupportLine.
D . Recommend the customer re-creates the volume groups.
-
A customer is currently using EMC’s Mirrorview/A. Their primary site is 400 kilometers away fromthe secondary site, and they have an RPO of 4 hours. What is the IBM equivalent product?()
A . Global Copy
B . Sync Mirror
C . Metro Mirror
D . TPC for Replicatio
-
Company.com has recently received a new p5-570 in the data center and intends to Micro-Partition the server. In which order should installation steps be taken?()
A . Connect to the network,power on the server,Micro-Partition the server
B . Connect to the HMC,power on the server,Micro-Partition the server,connect to the network
C . Power on server,connect to the network,Micro-Partition the server,connect to the HMC
D . Power on the server,connect to the HMC,Micro-Partition the server,connect to the network
-
A developer for the Company.com web site has been told that users may turn off cookie support in their browsers. What must the developer do to ensure that these customers can still use the web application?()
A . The developer must ensure that every URL is properly encoded using the appropriate URL rewriting APIs
B . The developer must provide an alternate mechanism for managing sessions and abandon theHttpSession mechanism entirely
C . The developer can ignore this issue. Web containers are required to support automatic URL rewriting when cookies are not supported
D . The developer must ass the string ?id=
-
Company.com is ordering a new p5-570 and planning for the option of using Capacity on Demand to activate additional resources in the future. Which of the following is a prerequisite to support the addition of CPUs or memory without an outage?()
A . Use Micro-Partitioning
B . Configure a Virtual I/O Server
C . Configure dynamic logical partitions
D . Activate Advanced POWER Virtualizatio
-
A Business Partner storage specialist is proposing an IBM System Storage DS5000 solution to aninstalled EMC customer. Which IBM resource should the Business Partner engage to assist withcompetitive sales strategies against EMC?()
A . Competeline
B . Executive Briefing Center
C . Competitive Benchmark Center
D . Field Technical Support Specialist (FTSS)
-
Company.com has decided to implement VPN for all network traffic. How might this might affect HACMP?()
A . Only the heartbeat IP network can exist in a VPN style network.
B . HACMp must have separate VPN’s for all ’non-service’ and ’service’ adapter networks.
C . If a VPN is used for IP traffic the heartbeating must be done over disk connections.
D . HACMP can exist in a VPN network environment,but special considerations must be addressed.
-
An EMC customer is interested in storage virtualization. The IBM storage specialist has anappointment to discuss the SAN Volume Controller. Before making the call, which EMC productshould the storage specialist review?()
A . VNX
B . VPLEX
C . V-Series
D . USP-V
-
Company.com would like to configure a virtual Ethernet between an AIX V5.3 LPAR and an AIX V5.2 LPAR. Which of the following options is necessary to complete this task?()
A . Remove the physical Ethernet adapters from the LPARs
B . Activate Advanced POWER Virtualization
C . Update microcode for the virtual adapters
D . Upgrade AIX V5.2 LPAR to AIX V5.3
-
Company.com recently experienced an unanticipated system outage when the VIO server was upgraded. The current p5-570 has six Micro-Partitions and a VIO server partition. How can a similar outage be avoided in the future?()
A . Use DLPAR to avoid an outage.
B . Deploy a redundant VIO server in the POWER5 system.
C . Add additional Host Bus Adapters and Network adapters to the VIO server.
D . Implement a standby server and move all partitions to it before applying future updates.
-
Company.com has four pSeries servers in their data center and wants to deploy multiple Micro-Partitions. Which of the following data center servers can be used for this purpose?()
A . p5-520 running Virtual I/O Server
B . p690 running AIX 5L V5.3
C . p5-510 running AIX 5L V5.2
D . p5-520 running two dedicated processor partitio